Lessons from Industrial Construction:

 

Insights from a brownfield factory expansion
A “ready for operation” factory means readiness not only of the process but also of the completeness of the buildings and the site infrastructure.  Roads must support vehicle movement, loading areas must remain accessible, and drainage must connect across the campus. These elements depend on coordinated ground levels and a clear understanding of existing site conditions.
Buildings often take priority, while roads, drains, and external works are treated as individual requirements with little or no priority. The site interfacing with the buildings often becomes a production bottleneck.
The consequences become apparent at their interfaces: an entrance does not align with a road, a loading bay sits below the surrounding ground, or a completed drain lacks a workable connection to the outlet.
A visit to a brownfield industrial project brought these challenges into focus. The observations from the visit offer practical lessons for planning infrastructure within an existing factory campus.

The project context

The visit was to review concerns about ongoing construction. Some of the challenges are as follows:
  1. The client required a material-movement corridor between an existing building and a new warehouse, while keeping the road in between the buildings.  
  2. Roads and drains were being planned as construction progressed, without a coordinated site infrastructure master plan.
  3. Excavation for another building was ongoing, so earth mounds were near the excavated areas.
  4. The available topographical survey was approximately 12 years old. Several construction activities had taken place since its preparation
  5. Groundwater had also caused difficulties during excavation.
The suggestions and recommendations were based on the conditions observed. This article records those observations and the planning lessons that emerged

1. Establishing a reliable topography of the existing site

A brownfield facility changes with every expansion. New buildings, paved areas, drains, utility installations and earthworks can alter both surface levels and the routes through which rainwater flows. A survey  therefore depends on whether it reflects current conditions.
At the expansion, the old survey did not reflect several subsequent developments. Coordination between building finished floor levels and external works was also lacking. Besten recommended a new topographical survey of the entire campus to establish the present topography.
The survey needed to record buildings, entrances, finished floor levels, non-building structures, loading areas, road levels, low points, drains, manholes, structures, trees, electrical poles and streetlights. External interface levels were equally important, including the adjoining industrial-area road and the invert levels—the levels at the bottom—of the receiving drains. A clearly identified, stable benchmark would allow all teams to work from the same reference.
Besten also suggested assessing the levelling of excavated earth in the construction area. Any such work would need coordination with the survey team so that temporary stockpiles and existing ground could be distinguished and relevant levels recorded before alteration.
Learning 1:  Any expansion must begin with an accurate record of what exists on the ground.

2. Planning the campus as one connected system

Planning roads and drains one construction package at a time can appear convenient. However, each completed element establishes levels and connections that influence the next phase. Without an overall plan, adjoining works may become difficult to reconcile.
At this factory, the industrial-area drain was reported to be lower than the site outlet. This was a potentially favourable condition for gravity drainage, but the level difference alone did not establish that the entire network would perform satisfactorily. The routes, gradients, capacity and receiving-drain conditions still required assessment.
We suggested creating a coordinated infrastructure plan covering building interfaces, road and ramp levels, loading areas, drainage routes and future development. The roads and drain works could then proceed in phases within that common framework.
Drainage planning also needed to account for runoff from building roofs and paved areas. Historical rainfall data for the location would help with building drainage and the drain network.
The lesson was to plan the whole campus before dividing the work into execution packages.

3. Loading bay an operational requirement

The finished-goods warehouse loading bay was situated in a low-lying area. Besten identified an inundation risk if surrounding levels and drainage were not adequately planned. The concern was more an inspection-related suggestion, given the area’s position and its potential to receive runoff.
For a warehouse, water accumulation at a loading bay can affect vehicle access, loading and unloading, and dispatch schedules. Its drainage therefore forms part of operational planning.
The suggested approach was to review the loading bay, the adjoining ground, and the wider drainage network. An updated survey would help identify where water could arrive from, where it should be intercepted and how it could be conveyed to the outlet.
Addressing these interfaces during construction can reduce the need for later alterations within an active dispatch area.

Looking beyond temporary groundwater management

Groundwater had caused excavation difficulties in an area reported to have previously been a water body. This raised questions about the performance of the completed works as well as the immediate construction challenge.
Besten recommended investigating the ground and groundwater conditions before selecting suitable long-term measures. A topographical survey would establish surface levels, but it would not, by itself, explain groundwater behaviour or the associated ground conditions.
The assessment would need to consider potential implications for fill, pavements, settlement and adjoining structures. The resulting design should address the conditions expected during operation, alongside any temporary measures required for construction.
The lesson was that resolving excavation difficulties does not necessarily resolve the underlying groundwater issue.

Questions to resolve before proceeding

Area of review
Key question
Survey and reference levels
Does the survey reflect current conditions, with a stable benchmark and verified external interface levels?
Building and road interfaces
Are entrances, roads, ramps and loading areas coordinated for their intended use?
Infrastructure planning
Does an overall campus plan guide each construction phase and allow for future development?
Runoff and drainage
Have roof and paved-area runoff, low points, network capacity and outlet conditions been assessed together?
Reuse of excavated earth
Has the material been assessed, with placement, compaction and pavement requirements defined?
Goods and vehicle movement
Does the proposed connection accommodate goods movement, vehicle access and drainage?
Groundwater
Have ground conditions been investigated and appropriate construction and long-term measures developed?
Verification of completed works
Will finished levels, compaction and drainage connections be checked and recorded?

Defining readiness beyond the building

The central learning from the visit was that site infrastructure must be designed around the facility’s full operation. A completed building may still be difficult to use if access, loading areas or drainage remain unresolved. Similarly, a completed drain provides limited value if its connection to the wider network has not been established.
Roads, drains, ramps, kerbs and landscaped areas all influence the relationship between buildings and their surroundings. Reviewing them together provides a stronger basis for construction sequencing, cost comparison and future expansion.
For a brownfield factory, this coordination starts with current site information and a shared infrastructure plan. It continues through detailed design, phased execution and verification of the completed works.
Planning an expansion within an existing factory campus? Besten Engineers and Consultants can help review site infrastructure requirements and coordinate the design before individual decisions become difficult to change.

Chennai

F-1,New No.26, Old No.24
Loganathan Nagar 1st Street,Choolaimedu,
Chennai- 600 094

Mobile: +91 87545 59600
Landline: +91 44 2361 1595 / 96
Email: roshini at besten.in

Besten is an Industrial architecture and holistic design consulting firm established in the year 1996. We use the power of a holistic design to create smart industrial designs that industry leaders love.

 

Other locations

Bengaluru                                     Ahmedabad
Mobile: +91 95914 55444              Mobile: +91 87545 59600
Email: crb at besten.in                   Email: cra at besten.in

Hyderabad                                    Pune
Mobile: +91 87545 59600              Mobile: +91 87545 93800
Email: crh at besten.in                   Email: crp at besten.in

©2020 Besten All rights reserved

Pin It on Pinterest